森林城市工程建设进度2017.10.15
Forest City Progress Update
海蓝湾
Cerulean
Bay
:
主体
结构已封顶,目前装
修施工阶段,铝窗已安装
至层,砌体施工至
31
层
Main structural works
completed, decoration
works in progress, Level
19 aluminium frame door
and window completed,
Level 31 masonry works
completed.
观澜海
Regalia Park
:
主体
结构施工阶段,最
慢第层
最快
第层
;
Plot 4:
M
ain structure
works
in construction
;
the lowest is Level 4
-
the highest is Level 7
海珀湾
Peony Littoral:
主体结构施工阶段,基础
结构完成至
70%
,主体结
构完成至
40%
M
ain structure works
in
construction
;
foundation works
completed 70%, main
structure works
completed 40%.